The project

What the Golden Pacific Powerlink actually is

A 500-kilovolt transmission line SDG&E plans to run from Imperial Valley to a new substation north of SONGS — cutting through more than five miles of Temecula Creek along the way.

Project overview

The Golden Pacific Powerlink is a proposed 500 kV extra-high-voltage transmission line from San Diego Gas & Electric (SDG&E), a regulated investor-owned utility whose service territory is San Diego and Orange counties — not Riverside County. Its parent company is Sempra Energy.

SDG&E says the line is needed to meet CAISO's 2022–2023 transmission planning requirements, moving power from southwestern generation areas to Southern California population centers, with a target commercial operation date of June 1, 2032. EHV lines like this typically carry 1,000–2,000 megawatts.

The core grievance: the corridor would route 500 kV towers through Temecula while delivering no direct benefit to the Riverside County residents who'd live beneath them.

The Temecula segment

The preliminary corridor runs from a proposed new substation north of SONGS eastward through Temecula, across the county line toward Palomar Mountain, and down to the existing Imperial Valley Substation. The contested portion follows the Temecula Creek corridor — land zoned Open Space Conservation — passing near Vail Ranch Middle School, the Santa Margarita River, and Pechanga.

Voltage
500 kV extra-high-voltage
Within city limits
~5 miles, I-15 to Anza Rd
Towers
21 steel lattice towers
Tower height
180–200 ft (may exceed 200 ft)
Tower spacing
900–1,200 ft apart
Right-of-way
~250 ft path (200 ft RoW + ~50 ft base)
Corridor sought
Reportedly up to 1,000 ft wide
Land
Temecula Creek — Open Space Conservation

How it gets approved

Transmission lines above 50 kV are approved by the California Public Utilities Commission (CPUC) — five commissioners appointed by the Governor. SDG&E's own materials lay out a five-step process, and Temecula was only notified at step 4, after the project had already been planned and approved:

  1. 1California Energy Commission (CEC) — forecasts statewide energy demand.
  2. 2CPUC — sets generation/storage planning via the Integrated Resource Plan.
  3. 3CAISO — decides where lines go and picks the solution in its Transmission Plan.
  4. 4SDG&E — early engineering, environmental studies, community outreach. (← Temecula first notified here.)
  5. 5CPUC + state/federal agencies — review under CEQA/NEPA, approve, and grant rights-of-way.

Local government can't veto the project — but its input, and yours, becomes part of the official record the CPUC must consider. See how to take action →

Claimed impacts & concerns

Several figures below come from community advocacy flyers. We label these as community-sourced and are verifying them against primary sources before treating them as established fact.

Construction footprint

21 towers ≈ 84 concrete footings (each ~5 ft wide × 50 ft deep). Estimated ~225 concrete trucks plus thousands of trucks for access-road gravel along the creek.

Property values

Community estimates: up to 40% decrease within the viewshed, up to 20% within 1,000 ft, up to 5% in surroundings.

Wildfire & safety

Concern that high-voltage lines in a high-wind corridor raise wildfire risk and complicate firefighting.

Health & EMF

Magnetic-field concerns near the line; field strength drops sharply with distance. Health claims are flagged for verification.

School setback

California Dept. of Education guidance calls for a 350 ft setback for 500–550 kV lines. A community analysis maps part of Vail Ranch Middle School inside that zone.

Scenic & quality of life

Towers as tall as a 20-story building over Temecula Creek, plus noise concerns and habitat disruption to the creek and Santa Margarita River.

Several of these deserve a closer, sourced look — explore the issues in depth →

Precedent: the Sunrise Powerlink

In 2008, SDG&E's Sunrise Powerlink faced fierce opposition over a similar path through Anza-Borrego. The CPUC rejected that route as “environmentally unacceptable and infeasible,” citing more than 50 significant, unavoidable impacts to the park. SDG&E argues today's route can co-locate with a 1930s-era 69 kV line on 50-ft wooden poles — but opponents note weathered wooden poles are not comparable to 200-ft steel lattice towers in a 200-ft right-of-way.

Source: Los Angeles Times, May 17, 2026

See how this unfolded — and where it's headed.